Project

Wastewater Tank Lining & Insulation Restoration

Interior lining rehabilitation and exterior spray foam insulation of a wastewater treatment tank serving a vitamin manufacturing facility.

Request a Quote (RFQ)
Services

Tank & Trench Liners, Abrasive Blasting, Protective Coatings, Insulation & Spray Foam

Environment

Water & Wastewater Treatment, Food & Beverage

Location

Palmyra, Wisconsin

Year

2025

Green Peak rehabilitated an existing industrial wastewater treatment tank at a vitamin manufacturing facility in Palmyra, Wisconsin. The original interior protective liner had deteriorated, leaving sections of the substrate exposed. The project addressed two distinct needs: restoring the interior lining and insulating the exterior to reduce the risk of freezing during Wisconsin winters.

The failed interior liner was removed by brush blasting in accordance with the coating manufacturer’s specification. Proper surface preparation was a key part of the restoration because the new lining depends on the condition of the substrate beneath it. Following preparation, Green Peak applied a high-build pure polyurea lining at 100+ mils, as specified by the facility's engineering department for its particular wastewater service conditions.

The exterior was also prepared and insulated with spray-applied polyurethane foam. The exterior insulation system was intended to reduce heat loss and the risk of freezing in the tank during cold weather. The foam was then protected with OR 80SLM Silver Lining Membrane, a pure polyurea coating from Oak Ridge Foam & Coating Systems of Green Lake, Wisconsin.

The project photographs document the original failed lining, abrasive surface preparation, interior work in progress and the completed insulated, coated exterior. No finished interior photographs are included. By addressing the interior and exterior as separate systems, Green Peak was able to rehabilitate the existing asset for its intended industrial service. Coating compatibility, insulation thickness and freeze protection requirements depend on the individual tank, wastewater chemistry and operating conditions.

Interior lining and exterior insulation

The interior photographs show the original condition and work in progress. The finished photographs show the completed exterior insulation and protective coating.

Abrasive surface preparation

Abrasive surface preparation

The failed interior lining was removed by brush blasting per the coating manufacturer’s specification, and the substrate was prepared for the new lining.

Spray-applied lining

Spray-applied lining

The new pure polyurea lining was applied to the engineering department's specified thickness of 100+ mils.

Interior work in progress

Interior work in progress

Interior restoration in progress. This is not a finished liner photograph.

Insulated exterior

Insulated exterior

Spray polyurethane foam and OR 80SLM Silver Lining Membrane protect the exterior insulation system.

Exterior coating manufacturer: Oak Ridge Foam & Coating Systems, OR 80SLM Silver Lining Membrane.

Project photography

32 actual field photos. Select a photograph to view it in full.

Wastewater Tank Lining & Insulation Restoration: Completed insulated and coated tank exterior 1Wastewater Tank Lining & Insulation Restoration: Completed insulated and coated tank exterior 2Wastewater Tank Lining & Insulation Restoration: Completed insulated and coated tank exterior 3Wastewater Tank Lining & Insulation Restoration: Completed insulated and coated tank exterior 4Wastewater Tank Lining & Insulation Restoration: Completed insulated and coated tank exterior 5

Project starter

Start your project with a conversation.

Tell us about your tank & trench liners needs, and we will develop a scope for your facility.